This afternoon, City Councils Audit and Finance Committee received an expanded report from the Office of the City Auditor on the costs of postponing completion of Water Treatment Plant No. 4. And afterward, council members who had questioned finishing the plant on economic grounds begrudgingly concluded they will not press for a delay of completion.
Scrubbing estimates from WTP4 contractor CDM on what a five or ten year postponement of the plant would cost, the OCA stated it found $100 million of CDMs five-year shutdown costs ($138 million) and $155 million of CDMs ten-year estimate ($206 million) reasonable. The numbers led Bill Spelman, who had pushed for the OCAs evaluation, to concede Were talking about numbers which are sufficently large that all the nickel and diming in the world isnt going to change something fundamental. While still arguing against the need for the plant, Spelman said, I think we ought to get through it, and refocus energy on more urgent needs, including conservation and stable water rates and fees.
(When reiterating his belief that, due to declining peak usage days, WTP4 wasnt needed, Spelman happened onto an intriguing line-of-thought: it might make more financial sense to postpone WTP4 indefinitely, as re-start costs comprised a healthy portion of the expense an option not fully explored by activists opposing the plant, who maintained the polite fiction the postponement would be a temporary affair. Neither here nor there, but )
After the committee accepted the auditors findings, Spelman, Sheryl Cole, and Chris Riley (who also sat in on the committees meeting) issued a press release stating they sought no further postponement of the plant.
So whats next? With postponement off the table, well likely see continued piecemeal opposition to plant components, such as the Save Our Springs Alliances scorched-earth take on the contracting for the plants Jollyville transmission main, and continuing environmental concerns surrounding the main, voiced at the meeting today by Laura Morrison. But at this point, it looks like its full speed ahead for the long controversial plant.
Below, a copy of the OCAs presentation.
City Auditor Presentation on WTP4 Postponement Costs
HEY! Sign up for the Hustle’s weekly e-mail newsletter, recapping news, politics and more every Friday. Don’t worry, we’ll never spam or sell your address. Visit here, enter your info, and click ‘City Hall Hustle.’
Got something you wanna show the Hustle? Email it to wells [at] austinchronicle.com, tweet it @CityHallHustle, drop by the Hustle’s Facebook or Tumblr page, or leave a comment in the section below.
This article appears in September 16 • 2011.