Council Opponents Concede on WTP4

The city auditor brings the latest numbers on a WTP4 shutdown

Stopping construction on the WTP4 project would be too costly for the city, council members say
Stopping construction on the WTP4 project would be too costly for the city, council members say (Photo by John Anderson)

As the Chronicle headed to press Wednesday, City Council's Audit and Finance Committee received an expanded report from the Office of the City Auditor on the costs of postponing completion of Water Treatment Plant No. 4. And after crunching the numbers, council members who had questioned finishing the plant on economic grounds begrudgingly concluded that "they will not press for a delay" of completion.

In late August, WTP4 contractor CDM released work-stoppage estimates that tabulated totals for a five-year and 10-year postponement at $138 million and $206 million, respectively, on top of the $367 million in currently remaining construction costs. In its estimate, CDM also included indirect but related costs, such as building new infrastructure (a pump station, pipelines, etc.), which it says would raise the current baseline cost of WTP4 construction ($508 million) by either $253 million (five-year postponement) or $486 million (10-year postponement).

An interim briefing doc from the OCA did not delve into any alternative infrastructure a WTP4 shutdown might require, but it did confirm many of the contractor's findings. CDM found $10.3 million in hard shutdown costs in both five- and 10-year scenarios ($3.7 million for engineering, $6.6 million for contract termination) instead of CDM's $79 million, but forecast a 3% inflation factor, adding $68 million and $135 million, respectively. CDM's predicted legal expenses ($12 million) and site protection costs ($3 million to $4 million) were said to "appear reasonable"; OCA also called roughly half of restart costs "reasonable" and said they were waiting for additional info from CDM before weighing in on the other half (engineering services, at $11.5 million). A $20 million mobilization/start-up expense for reinitiating construction was also still being analyzed, "pending additional information from CDM." Also, the OCA wrote: "We analyzed CDM and the WTP4 contractors to determine if there were any related-party issues that could present a conflict of interest [as has been charged by some critics of the project]. ... We found no evidence of any conflict of interest. We also determined CDM is a recognized engineering services firm."

At Wednesday's committee meeting, the OCA concluded that it found $100 million of CDM's five-year shutdown costs ($138 million) and $155 million of CDM's 10-year estimate ($206 million) "reasonable." (Their overall totals included operation and maintenance savings from postponing WTP4.) The numbers led Bill Spelman, who had pushed for the OCA's evaluation, to concede, "We're talking about numbers which are sufficiently large that all the nickel-and-diming in the world isn't going to change something fundamental." While he still feels the plant isn't needed, Spelman said, "I think we ought to get through it" and refocus energy on "more urgent needs," including conservation and stable water rates and fees – sentiments that were echoed by committee members Laura Morrison, Kathie Tovo, and Sheryl Cole.

After the committee accepted the auditor's findings, Spelman, Cole, and Chris Riley (who also sat in on the committee's meeting) issued a press release stating they sought no further postponement of the plant.

Got something to say on the subject? Send a letter to the editor.

A note to readers: Bold and uncensored, The Austin Chronicle has been Austin’s independent news source for over 40 years, expressing the community’s political and environmental concerns and supporting its active cultural scene. Now more than ever, we need your support to continue supplying Austin with independent, free press. If real news is important to you, please consider making a donation of $5, $10 or whatever you can afford, to help keep our journalism on stands.

Support the Chronicle  

READ MORE
More Water Treatment Plant No. 4
WTP4: What's $15 Million Among Friends?
WTP4: What's $15 Million Among Friends?
One expects Council will be more vigilant the next time around

Mike Kanin, Dec. 14, 2012

WTP4: Running on Overruns?
WTP4: Running on Overruns?
Austin Water wants more money for WTP4

Mike Kanin, Oct. 19, 2012

More City Auditor
Audit: Uri Was Bad, City Made It Worse
Audit: Uri Was Bad, City Made It Worse
Report faults shortcomings in disaster preparedness in city's winter storm response

Austin Sanders, Nov. 12, 2021

10-1, Step One: Finding Commissioners
10-1, Step One: Finding Commissioners
The public comment period on the new districting process was extended a week for more input

Elizabeth Pagano, Jan. 18, 2013

More by Wells Dunbar
Top 10 City Council Stories
Top 10 City Council Stories
Dais and months

Jan. 6, 2012

City Hall Hustle: The Hustle Bids Farewell ...
City Hall Hustle: The Hustle Bids Farewell ...
To the beating hearts of a great city

Dec. 30, 2011

KEYWORDS FOR THIS STORY

City Auditor, Water Treatment Plant No. 4, Office of the City Auditor, Audit and Finance Committee, CDM

MORE IN THE ARCHIVES
One click gets you all the newsletters listed below

Breaking news, arts coverage, and daily events

Keep up with happenings around town

Kevin Curtin's bimonthly cannabis musings

Austin's queerest news and events

Eric Goodman's Austin FC column, other soccer news

Information is power. Support the free press, so we can support Austin.   Support the Chronicle