WTP4: What's $15 Million Among Friends?

One expects Council will be more vigilant the next time around

Mayor Lee Leffingwell, speaking at the WTP4 site in 2011, defended the project's $15 million overrun.
Mayor Lee Leffingwell, speaking at the WTP4 site in 2011, defended the project's $15 million overrun. (Photo by John Anderson)

By the time Austin Water utility staff found themselves asking for an extra $15 million from a dais that included at least four frustrated Council members last Thursday morning, the massive Water Treatment Plant No. 4 project had been through multiple iterations and decades (that's decades) of debate. Along the way, it picked up multiple levels of opposition – from environmentalists, from fiscal conservatives, from neighborhood groups, from anti-growth Keep Austin Weirdos. By now, everything about the project is front-loaded with controversy. If there were ever a city infrastructure effort that was going to make a relatively small (percentage-wise, if you believe the city's numbers) cost overrun look like a true pitchforks-and-torches moment, this is it.

The history goes roughly like this: Way back in 1984, Austin voters approved bond money to pay for land for a new water treatment plant, but for various reasons, a series of City Councils deferred groundbreaking and even site selection. In the last decade, environmental concerns about the initial site chosen kept dirt from moving and – after a location move, much more debate over the need and the timing, and a very split series of Council votes – Council finally OK'd a $508 million dollar deal to build the thing, roughly $359 million of which was dedicated to construction ... in 2009. That's a full quarter century of hemmin' and hawin'.

The agreement approved by Council is called "Construction Manager at Risk," because it's supposed to shift portions of risk to the construction firm – MWH Con­struct­ors – and away from the city. Thurs­day morning, some Council members continued to suggest that they weren't quite clear – at least not when it counted – on what risk they were being insulated from. It's hard to blame them. AW staff and city management point to the fact that they never did quite say that the $359 million in construction costs were guaranteed – but they also never did quite say that they weren't. And that's on top of the fact that the phrase "guaranteed maximum price" was thrown around with some abandon. Council Member Bill Spelman summed up his colleagues' predicament. "I think we probably played it just exactly the way we should have," Spelman said of Coun­cil's approval of the Construction Man­ager at Risk contract, before adding a hefty caveat pointed at city management – "except the Council needed to know what the game was. And I did not know what the game was; I know at least a couple of us didn't, and I suspect most of us didn't."

After it became clear – perhaps, to city management, as many as six months before Council formally heard about it – that $359 million wouldn't do the trick, AW staff came back for the additional $15 million. They did so to a chorus of "I told you so"s from familiar advocates. Save Our Springs' Bill Bunch even got himself thrown out Thurs­day for yelling from the audience at Mayor Lee Leffingwell.

In response to the criticism, Leffingwell pointed to what he saw as a .8-3.3% cost overrun on the project, even after its $15 million price tag bump. That number, he suggested, is fairly impressive for a project this size. For the record, Council gadfly Paul Robbins has suggested that, given construction cutbacks – including an entire transmission main and a scaling-back of a pump station in the wake of news of the overrun – plus contingencies used, the true overrun cost is closer to $60 million. That's a 10-16% overage, a figure that is not so impressive. (Austin Water Director Greg Meszaros told Council that there were also unanticipated additional costs addressing neighborhood and environmental concerns.)

All together, it's enough to make observers wonder why all this had to happen to the one project that it positively couldn't happen to – in an episode that could have implications down the line. "Never, ever, ever relinquish Council oversight on a project," said Sierra Club vice chair Roy Waley, referring to the Construction Manager at Risk process.

After Thursday's meeting, Council Mem­bers Bill Spelman and Laura Morrison both told online In Fact Daily that this messy experience with the process shouldn't cloud the whole idea of Construction Man­ag­er at Risk as a viable option for some city infrastructure projects. And, indeed, at least one other construction effort – the new Central Library – is anticipated for such a contract. One would expect that Council members will be more vigilant the next time around.

Got something to say on the subject? Send a letter to the editor.

A note to readers: Bold and uncensored, The Austin Chronicle has been Austin’s independent news source for over 40 years, expressing the community’s political and environmental concerns and supporting its active cultural scene. Now more than ever, we need your support to continue supplying Austin with independent, free press. If real news is important to you, please consider making a donation of $5, $10 or whatever you can afford, to help keep our journalism on stands.

Support the Chronicle  

READ MORE
More WTP4
Top 10 Environmental Stories
Top 10 Environmental Stories
Save Our Springs' anniversary, Al Armendariz's move, and the bag ban

Amy Smith, Jan. 4, 2013

Then There's This: Water for Sale
Then There's This: Water for Sale
WTP4 has to pay for itself, by hook or by crook

Amy Smith, Nov. 30, 2012

More Water Treatment Plant No. 4
WTP4: Running on Overruns?
WTP4: Running on Overruns?
Austin Water wants more money for WTP4

Mike Kanin, Oct. 19, 2012

Council Opponents Concede on WTP4
Council Opponents Concede on WTP4
The city auditor brings the latest numbers on a WTP4 shutdown

Wells Dunbar, Sept. 23, 2011

More by Mike Kanin
Council-Staff Tension Spills Over in Budget Talks
Council-Staff Tension Spills Over in Budget Talks
Spelman and Martinez drill staffers over cost projections and turnover

Aug. 30, 2013

Gómez Pushes Road Plan Near Racetrack
Gómez Pushes Road Plan Near Racetrack
Commissioner says she's concerned about access and safety issues in her precinct

Aug. 30, 2013

KEYWORDS FOR THIS STORY

WTP4, Water Treatment Plant No. 4, City Council, Austin Water, Austin Water Utility, Greg Meszaros, Bill Spelman, Lee Leffingwell, Laura Morrison, Central Library, Austin Public Library

MORE IN THE ARCHIVES
One click gets you all the newsletters listed below

Breaking news, arts coverage, and daily events

Keep up with happenings around town

Kevin Curtin's bimonthly cannabis musings

Austin's queerest news and events

Eric Goodman's Austin FC column, other soccer news

Information is power. Support the free press, so we can support Austin.   Support the Chronicle